Delhi Development Authority v. Archana Khanna and Ors.
Background
The land award in this case was dated 7 January 1999. No stay was ever in operation against DDA taking possession, yet DDA never actually took physical possession of the land. This was the key fact relied on by the landowner to argue that the acquisition had lapsed under the 2013 land acquisition law.
Decision Breakdown
The Supreme Court held that since the award predated the relevant cut-off, there was no stay in force, and possession was never taken, Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 squarely applied, and the acquisition had to be declared lapsed. The appeal was accordingly dismissed, with no order as to costs. Unlike the companion batch of DDA appeals decided the same month, this particular order (dated 16 August 2016) did not include the usual one-year grace period for DDA to initiate fresh acquisition proceedings.
Lesson Learnt
Holding an old land acquisition award on paper, without ever taking possession or paying compensation, can cause the acquisition to lapse entirely under the 2013 Act, and courts will enforce this even without granting the acquiring authority a fresh opportunity if the facts clearly meet the lapsing conditions.