Delhi Development Authority v. Habeeb Khan and Others
Background
This is one of a batch of near-identical appeals filed by the Delhi Development Authority (DDA) against individual landowners whose acquired land was held to have lapsed under Section 24(2) of the 2013 Land Acquisition Act. The legal question here was identical to the one already settled by the Supreme Court in a lead case, Civil Appeal No. 8477 of 2016 (arising from SLP(C) No. 8467 of 2015).
Decision Breakdown
The Court held the issue was squarely covered against DDA by the lead judgment and dismissed the appeal on that basis. It granted DDA one year from the date of the order to initiate fresh acquisition proceedings by issuing a new Section 11 notification, failing which DDA, if in possession, was directed to return physical possession of the land to the original owner.
Lesson Learnt
Where an acquisition lapses for procedural default, a landowner can expect the acquiring authority to be given one final, time-bound opportunity to restart the process correctly rather than losing the land claim outright and immediately.