Delhi Development Authority v. Praveen Jain
Background
The Delhi Development Authority had acquired land many years earlier, but had not taken physical possession of it and had not paid/deposited compensation in the manner required. The landowner, Praveen Jain, successfully argued before the High Court that the acquisition should be treated as lapsed under Section 24(2) of the new 2013 land acquisition law. DDA appealed to the Supreme Court against that finding.
Decision Breakdown
The Supreme Court held that the point raised by DDA was already settled against it by an earlier decision of the same day, Civil Appeal No. 8477 of 2016 (arising out of SLP(C) No. 8467 of 2015), which is treated as the lead/governing judgment on this recurring issue. Following that precedent, the Court dismissed DDA's appeal. However, taking into account the specific facts, the Court gave DDA one year from the date of the order to start a fresh acquisition by issuing a new notification under Section 11 of the 2013 Act, failing which DDA (if it was in possession) had to hand the land back to the original owner.
Lesson Learnt
Where a government land-acquiring authority has not taken possession of acquired land or paid compensation within the time limits set by the Right to Fair Compensation and Transparency in Land Acquisition Act, 2013, the old acquisition can lapse, but courts may still give the authority a limited window to start the process again rather than losing the land outright.