Delhi Development Authority v. Ran Singh and Ors.
Background
The Delhi Development Authority (DDA) appealed against a decision (and connected appeals involving similar facts) that went against it on the question of whether its land acquisition proceedings had lapsed under Section 24(2) of the 2013 Land Acquisition Act. After condoning delay and granting leave, the Court noted that the point of law involved was already settled against the DDA by two of its own earlier decisions (in Civil Appeal No. 8477 of 2016 and Civil Appeal No. 5811 of 2015).
Decision Breakdown
Following its own binding precedent, the Supreme Court dismissed the DDA's appeals. However, taking into account the peculiar facts, the Court granted the DDA one year's liberty to initiate fresh land acquisition proceedings under Section 24(2) of the 2013 Act by issuing a fresh Section 11 notification. The Court made clear that if no fresh notification issued within that year, the DDA, if still in possession, would have to return physical possession of the land to the owner. All pending applications were disposed of with no costs.
Lesson Learnt
Even where a landowner wins on a lapsed-acquisition point, courts can calibrate relief practically: here by giving the acquiring authority a fixed window to restart the process properly, rather than leaving the land's status in permanent limbo.