Delhi Development Authority vs. Asha Prakash and Ors.
Background
A person who bought the land after it had already been notified for acquisition (a "subsequent purchaser") filed a writ petition in the Delhi High Court in 2015 seeking a declaration that the acquisition had lapsed under Section 24(2) of the 2013 Act because compensation had not been paid to the original owners. The DDA objected that a subsequent purchaser has no right to bring such a challenge. The High Court rejected that objection relying on Government (NCT of Delhi) vs. Manav Dharam Trust (2017), and then, following Pune Municipal Corporation (2014), declared the acquisition lapsed.
Decision Breakdown
The Supreme Court allowed the DDA's appeal on two independent grounds. First, Manav Dharam Trust is no longer good law: in Shiv Kumar vs. Union of India (2019) and later in DDA vs. Godfrey Philips and Delhi Administration vs. Pawan Kumar (both 2022), the Supreme Court held that a subsequent purchaser has no locus to challenge an acquisition or claim that it has lapsed, so the High Court committed a grave error in entertaining the petition at all. Second, the Pune Municipal Corporation decision the High Court applied on the merits was overruled by the Constitution Bench in Indore Development Authority vs. Manoharlal (2020), under which lapse requires that neither possession was taken nor compensation paid. The High Court's judgment was quashed and the appeal allowed with no order as to costs.
Lesson Learnt
If you buy land after the government has already started acquiring it, you step into the transaction with your eyes open. You cannot later go to court to have the acquisition declared lapsed. Only the original landowner (as on the date of the acquisition notification) has standing to raise such a challenge.