National Campaign Committee for Central Legislation on Construction Labour (NCC-CL) v. Union of India
Background
This is an interim order, not a final judgment. This public interest case monitors two laws for the welfare of building and construction workers. More than Rs. 32,000 crore had been collected as cess nationally, but less than a quarter had been spent on workers.
Decision Breakdown
This is an interim order, not a final judgment. The Court reviewed compliance State by State, issued further directions to governments, including to fix timelines, and listed the petition on 01.05.2018 to check that timelines had been fixed.
Lesson Learnt
There is no final ruling yet. The Court is monitoring whether cess collected for construction workers actually reaches them.