National Highways Authority of India vs Sheetal Jaidev Vade & Ors.
Background
The respondents' land was acquired by the National Highways Authority of India (NHAI), and an Arbitrator later enhanced the compensation payable. NHAI challenged the enhanced award under Section 34 of the Arbitration Act but did not obtain a stay of the award. Rather than filing execution proceedings to enforce the award, the landowners filed a writ petition directly in the Bombay High Court (Aurangabad Bench) seeking a mandamus directing NHAI to deposit the award amount, and the High Court allowed them to withdraw a large portion of it pending the Section 34 challenge.
Decision Breakdown
The Supreme Court held that the High Court erred in entertaining a writ petition under Article 226 to execute an arbitral award, since an award is enforceable only through execution proceedings before the competent Executing Court, allowing High Courts to act as executing courts via writs would open the floodgates to similar petitions and blur the line between constitutional and execution jurisdiction. The Court disapproved of this practice going forward. However, rather than fully setting aside the High Court's order, it followed its own recent similar ruling in a comparable NHAI case and modified the directions: NHAI was ordered to deposit 50% of the arbitral award amount with the Executing Court within four weeks (releasable to the landowners unconditionally), with the District Court asked to decide the pending Section 34 challenge within six months, after which the balance amount would be deposited and released subject to the outcome.
Lesson Learnt
A party seeking to enforce an arbitral award must use the statutory execution process before the competent court, not a writ petition, but courts may still fashion a practical interim payment arrangement to prevent landowners from indefinitely being kept out of compensation while a challenge to the award remains pending.