Background
This order sends the case back; it does not decide the dispute. The dispute is about who owns certain land in Arunachal Pradesh and who is entitled to the compensation deposited for it by the Army. The parties agreed not to insist on land acquisition proceedings under the Land Acquisition Act, 1894.
Decision Breakdown
This is not a final decision on the dispute. The Court set a procedure in which the District Judge, Lohit District (Tezu), acts as a Reference Court to identify the rightful owners and apportion the compensation. This is to be completed within three months. The Court did not itself decide which claimants are entitled.
Lesson Learnt
There is no final ruling yet on who is entitled to the compensation. The Court set the procedure and a three-month deadline for the District Judge to decide.