The appellant society's land had been acquired by the State, and compensation money for it was lying deposited in the Reference Court pending resolution of a dispute. The society approached the Supreme Court seeking permission to withdraw this deposited compensation amount. Since the interests of both sides could be protected through appropriate conditions, the Court found it unnecessary to even issue notice to the respondents before deciding the matter.
Decision Breakdown
The Supreme Court condoned the delay in filing, granted leave to appeal, and then directly addressed the withdrawal request. It permitted the appellant to withdraw 50% of the deposited compensation amount without furnishing any security, and allowed withdrawal of the remaining 50% upon furnishing security to the satisfaction of the Reference Court. The Court clarified that this arrangement would apply both to amounts already deposited and to any further deposits made in the future. The appeal was disposed of in these terms.
Lesson Learnt
When compensation for acquired land is held up in court pending a dispute, a claimant can seek interim release of a portion of the funds (often half) without security, with the balance releasable on furnishing security: a practical way to access part of one's money while the underlying dispute continues.