State of Himachal Pradesh & Ors. vs Rajiv & Anr.
Background
In 1996 the Himachal Pradesh government built the Banuti-Pahal road through the land of the respondents in Village Tikkari, Shimla district. A notification under Section 4 of the Land Acquisition Act, 1894 had been issued on 17 May 1996 but was allowed to lapse, and no compensation was ever paid. The State's position was that the road was built at the landowners' own request and on an oral understanding that they would not claim compensation, though nothing was ever put in writing. About 20 years later the landowners filed a writ petition; a Single Judge of the High Court directed the State to initiate acquisition proceedings. The State's appeal to the Division Bench was filed 354 days late and dismissed on limitation, so the State came to the Supreme Court, which chose to decide the matter on merits rather than send it back.
Decision Breakdown
The Court held that since the State's only real defence was delay, and there was no written consent showing the owners had voluntarily given up their land, the owners were entitled to compensation for land the State had used without acquiring it under the 1894 Act (following Sukh Dutt Ratra vs State of Himachal Pradesh, 2022). Exercising its extraordinary powers under Articles 136 and 142 to do complete justice, it directed that 17 May 1996, the date of the lapsed Section 4 notification, be treated as the deemed date of acquisition, with compensation calculated at the market value on that date plus all statutory benefits under the 1894 Act. However, because the owners had waited 20 years to approach the court, they were denied interest for the period from 17 May 1996 until the writ petition was filed. The State was directed to allow the owners to lead evidence on the 1996 market price, calculate the compensation, and pay it within two months of calculation, with the whole exercise to finish within six months.
Lesson Learnt
The State cannot take private land for a public project without paying for it, and a long delay by the owner does not wipe out the right to compensation, though the delay can cost the owner the interest for the years they sat silent. If you agree to give up land for a road or other public work, get the terms in writing; an oral "no compensation" understanding will not protect the State later.