State of U.P. & Ors. v. Abdul Ali & Ors.
Background
The State had acquired land under the Land Acquisition Act, 1894, and passed its final Award in 1989. A particular plot belonging to the respondents was not covered by the original Section 4(1) notification or the Section 6 declaration, yet the Award purported to cover it. Years later, the State issued "corrigenda" in 1992 and 1993 trying to retroactively bring that plot within the original notification and declaration.
Decision Breakdown
The Supreme Court held that once an Award has been passed, there is no scope to correct or expand the underlying Section 4(1) notification or Section 6 declaration: the Act only allows correction of clerical mistakes in the Award itself, under Section 13A, and only within six months. Since there was never a valid notification or declaration for this particular plot, the Award could not validly cover it, and the attempted corrigenda could not cure that defect after the fact. The appeal was dismissed, but the Court clarified the State remains free to start a fresh, lawful acquisition for the same plot if it wishes.
Lesson Learnt
The government cannot paper over a missing or defective land-acquisition notification by issuing corrections years after the Award: the proper notification must exist before the Award, not after.