Surinder Ahuja & Anr. v. State of Punjab & Anr.
Background
Land belonging to farmers across six villages in Fazilka district, Punjab was acquired in 2000-2001 to build the Aspal Extension Drain, an 18.42-km irrigation canal. Landowners disputed the compensation through 195 appeals in the Punjab and Haryana High Court, which in 2019 replaced the original uniform per-acre rate with a "radial step-down model" (compensation decreasing with distance from the road) and cut various other heads of compensation. These 47 appeals, spanning multiple villages, challenged that High Court ruling.
Decision Breakdown
The Supreme Court set aside the High Court's radial step-down model and restored a uniform market value of ₹5,00,000 per acre across all the villages, finding the distance-based reduction unjustified. It affirmed the High Court's other rulings, however: fruit-tree compensation limited to the 280 trees actually pleaded, severance charges restored at 50% of market value for the remaining unacquired land, and tubewell displacement compensation kept at a flat ₹50,000 per tubewell (rejecting a private valuation report whose author was never produced for cross-examination). The Court also upheld denying extra statutory solatium/interest on the tubewell and severance components, applying those benefits only to core market-value compensation. Authorities were given six months to pay the additional compensation.
Lesson Learnt
In land acquisition disputes, courts will readily restore a uniform, fair market rate across similarly-situated parcels, but ancillary compensation heads (like moveable equipment such as tubewells) still require the claimant to prove their case with admissible evidence, not private reports whose authors were never examined in court.