The Mayor Municipal Corporation (Aurangabad) v. Govind Bajirao Navpute & Ors.
Background
The Aurangabad Municipal Corporation notified a draft development plan in February 2016 under the Maharashtra Regional and Town Planning Act. Residents and civic groups challenged the plan before the Bombay High Court (Aurangabad bench), arguing it was prepared beyond the statutory time limit, several public amenities and green spaces were quietly dropped, and the extension of time granted to prepare the plan was legally invalid. The High Court agreed, quashed the plan and the extension order, and directed that the remaining planning work be completed by specified Town Planning officials instead of the Municipal Corporation. The Corporation and other affected parties appealed to the Supreme Court.
Decision Breakdown
The Supreme Court declined to interfere with the High Court's judgment. It held that the planning authority had indeed failed to prepare the draft development plan within the statutory time frame under Section 26 of the Act, triggering a specific legal provision (Section 21(4A)) that shifts responsibility for completing the plan to a designated Town Planning officer. The Court also noted that, during the pendency of these appeals, the State Government had itself directed preparation of a fresh, combined development plan for the city's original and expanded areas, making it unnecessary to revisit the technical arguments about whether the time limits were strictly mandatory. The appeals were accordingly dismissed.
Lesson Learnt
Statutory deadlines for government planning processes are taken seriously by courts: if an authority misses them, the law can transfer the task to another designated official, and citizens' groups can successfully challenge a development plan that strips away previously promised public spaces.