Jai Singh vs. Delhi Development Authority
Background
A contractor built DDA housing that took over four years instead of 18 months; his final bill of roughly Rs. 1.57 crore went unpaid, prompting a 2000 lawsuit covering several separate claims.
Decision Breakdown
On the main claim, the Court found DDA had no credible proof the contractor owed money for third-party rectification work and decided this claim in his favour for Rs. 41,77,809 plus 9% interest. All other claims were rejected for lack of proof (no timely protest, no real evidence).
Lesson Learnt
In a money claim against a government body, bald assertions aren't enough: a claimant must back each head of claim with real evidence; courts grant only what is actually proven.