M/s Telecommunication Consultants India Limited vs. M/s Rajput Construction

First Appeal from Order (Commercial) · CNR No. DLHC010277222023Decided 17 Nov 2026New Delhi Bench
FAO (COMM) 152/2023CNR: DLHC010277222023
Justice Avneesh Jhingan · Justice Shail Jain

Background

Telecommunication Consultants India Limited won a road-work tender in Madhya Pradesh and passed the work on to Rajput Construction on a back-to-back basis. A dispute arose, and a sole arbitrator (a private judge chosen under the contract) gave an award in 2018 without Rajput Construction taking part. Rajput Construction challenged the award in May 2019, saying it first got a copy through an RTI request in March 2019, and argued that the arbitrator had been appointed by one side alone. The Commercial Court set the award aside on that ground but never decided whether the challenge had been filed in time.

Decision Breakdown

The High Court explained that Section 34(3) of the Arbitration and Conciliation Act allows three months from receipt of the award to challenge it, plus a further 30 days at most if there is good reason. Relying on Supreme Court rulings, it held that this limit is strict and the general power to excuse delay under Section 5 of the Limitation Act does not apply. The question whether the arbitrator's one-sided appointment broke Section 12(5) of the Act could be examined only if the challenge was first found to be within time. Because the Commercial Court skipped the time-limit question, its judgment was set aside and the case was sent back for fresh decision. The parties were told to appear before the Commercial Court on 14 December 2026, and that court was asked to decide quickly since the award dates from 2018.

Lesson Learnt

A party wanting to challenge an arbitration award must act within three months of receiving it, with at most 30 more days for good reason. A court must decide whether the challenge is in time before looking at its merits, however strong those merits seem.

Arbitration & Commercial LawSupreme Court of India

Neycer (India) Ltd. v. GMB Ceramics Ltd.

The Supreme Court set aside the Division Bench's judgment and restored the Single Judge's order limiting the award to Rs. 2 crore. It held that an arbitrator is a "creature of the contract and the reference" and cannot widen his own jurisdiction: once GMB itself limited its claim to Rs. 2 crore when appointing its arbitrator, it could not enlarge the claim by a later letter, and Neycer's participation on merits (while objecting all along) was not a waiver. The Court also agreed that the Rs. 2.03 crore awarded for brand-building advertising was speculative, since GMB's own audited accounts showed it actually spent only about Rs. 35.3 lakh, and that the Umpire wrongly treated Neycer as an insurer of five years of GMB's profits and loan interest. Because Neycer had already paid Rs. 4 crore (Rs. 2 crore principal plus Rs. 2 crore interest) under interim orders, and the dispute had run nearly four decades, the Court directed that this sum be treated as full and final satisfaction of the award, with each side bearing its own costs.

Decided 18 Nov 2026Read case
Arbitration & Commercial LawSupreme Court of India

Marino Dredgeco Ltd. v. Board of Trustees of the Port of Kolkata

The Supreme Court set aside the Division Bench's judgment, allowed the contractor's appeal and restored the arbitral award in full; the Port Trust's appeal, which sought to set aside the entire award, was disposed of. It held that the "shocks the conscience" / conflict with "basic notions of morality or justice" ground cannot be invoked as mere lip service: there must be a substantive, blatant reason, and a bill simply being large is not one (relying on Ssangyong Engineering and Somdatt Builders). The High Court had not even examined the measurements and invoices the arbitrator relied on, and re-examining them would itself have been a forbidden review of the merits; nor could the award be partly cut down under Gayatri Balasamy, since the re-dredging claim was one inseparable whole. The Court added that a government body gets no special treatment in arbitration, and the lack of a completion certificate (which the Port Trust itself did not issue) did not defeat payment for work actually done.

Decided 18 Nov 2026Read case
Arbitration & Commercial LawDelhi High Court

WAPCOS Limited vs. M P Khaitan & Anr.

The Court dismissed the appeal without costs. It explained that under Section 37(2)(b) a court can interfere with an arbitrator's interim order only if it is perverse, patently illegal or beyond the arbitrator's powers, and will not replace a plausible view with its own. WAPCOS argued that only it could foreclose under Clause 13 of the contract, but the Court said that clause empowers WAPCOS without forbidding the contractor from seeking foreclosure, read with Sections 51, 53, 54 and 55 of the Indian Contract Act, 1872, and noted the clause had not even been raised before the arbitrator. It also upheld the direction that WAPCOS take over the project and the decision to drop the Ministry, since the Ministry had not signed the contract and it was doubtful that the handing-over clause could bind it.

Decided 18 Nov 2026Read case
Arbitration & Commercial LawDelhi High Court

M/s Eastman Cast and Forge Ltd. vs. M/s Exact Developers & Promotors Pvt. Ltd.

The developer argued that only Gurugram courts could hear the case because the original builder-buyer agreement gave them exclusive jurisdiction. The Court disagreed: the buyer was suing on the separate settlement agreement, not seeking possession under the builder-buyer agreement, and since that settlement was signed in Delhi and the developer is located in Delhi, Section 20(c) of the Code of Civil Procedure (CPC) gave the Delhi High Court jurisdiction. The developer also claimed an oral understanding that the buyer would take the units instead if it could not raise the refund money. The Court rejected this because the written settlement contained no such term, and a written document excludes oral claims that contradict it. Applying the Supreme Court's test in Reliance Eminent Trading, it found the developer had no real prospect of defending the claim, called the defence "moonshine", and passed a decree for Rs. 4,07,81,000 with interest at 9% a year from 18 July 2023.

Decided 18 Nov 2026Read case
Arbitration & Commercial LawDelhi High Court

PRL Projects and Infrastructure Ltd. vs. State of Rajasthan

The Court did not decide the challenge on its merits. It noted that the related appeal had been disposed of on 28 October 2026, so the contractor could now use the liberty the Arbitral Tribunal had already given it. The appeal was disposed of with permission to file a fresh application before the tribunal, which is to be decided according to law without being influenced by the Court's remarks. The contractor's lawyer said the application would be filed within one week, the tribunal was requested to decide it within four weeks after that, and both sides were told not to seek needless adjournments.

Decided 17 Nov 2026Read case
Arbitration & Commercial LawDelhi High Court

Axis Finance Limited vs. Venkata Siva Prasada Rao Addanki & Anr.

The Court disposed of the petition and directed Axis Finance to start arbitral proceedings within 45 days. The existing interim arrangement will continue for those 45 days and, if arbitration begins in time, until the arbitral tribunal passes orders under Section 17 of the Act (the tribunal's own power to give interim relief). If arbitration is not started in time, the protection ends automatically. Once the tribunal is formed, this petition will be treated as a Section 17 application before it, and the tribunal may continue, change or cancel the arrangement. All rights and arguments of both sides, including on jurisdiction and entitlement to relief, were left open.

Decided 17 Nov 2026Read case
M/s Telecommunication Consultants India Limited vs. M/s…