Power Grid Corporation of India Ltd. v. TANGEDCO
Background
Power Grid Corporation (PGCIL), the central transmission utility, built two "LILOs" (Line-In Line-Out connections that loop a power line into a substation and back out) on the Tuticorin JV-Madurai line at the Tuticorin Pooling Station, commissioned on 4 and 8 January 2015. A power generator (Moxie Power Generation, formerly Coastal Energen) was supposed to build its own dedicated line to the pooling station but only did so on 27 October 2016; meanwhile its electricity flowed to TANGEDCO through PGCIL's network. The central regulator (CERC) accepted the LILOs' commercial operation dates and made the generator liable for transmission charges for this gap period (about Rs. 15.43 crore was in dispute), but APTEL reversed this, holding the LILOs were not put to use because further upstream lines to Salem and Madhugiri were not yet ready, and sent the operation-date question back to CERC.
Decision Breakdown
The Supreme Court allowed PGCIL's appeals, set aside both APTEL orders, and restored CERC's order. It held that the LILOs were a permanent, agreed part of the transmission plan approved in Standing Committee meetings (binding under Section 29(4) of the Electricity Act, 2003) and that the generator's power was in fact routed through them: the generator had itself admitted using the pooling station to evacuate power. Since transmission was never held up, the special rule for fixing the operation date when a line cannot be used because of another party's delay (Regulation 4(3)(ii) of the 2014 Tariff Regulations) did not apply, and CERC had rightly accepted the dates based on trial-operation and safety certificates. Relying on its earlier ruling in PGCIL v. Madhya Pradesh Power Transmission Co. (2025), the Court held the generator, which delayed its own dedicated line, must bear the LILO transmission charges from January 2015 to 27 October 2016.
Lesson Learnt
A company that uses shared infrastructure while delaying its own promised connection must pay for that use; it cannot avoid charges by arguing that other parts of the network were incomplete. Planning decisions agreed by all stakeholders at statutory planning meetings bind them.