Ankhim Holdings Pvt. Ltd. v. Zaveri Construction Pvt. Ltd.

Civil Appeal · 2026 INSC 137Decided 4 Feb 2026
C.A. No.-000779-000779 - 2026
Justice J.B. Pardiwala · Justice K.V. Viswanathan

Background

The appellants and the respondent had partnered on a slum redevelopment project in Mumbai, and their disputes were referred to arbitration before a retired judge. While arbitration was underway, the respondent company went into insolvency proceedings (CIRP) before the NCLT, triggering a moratorium under Section 14 of the Insolvency and Bankruptcy Code (IBC). Certain arbitral hearings and orders (permitting sale of some flats) took place between March and August 2022, a period that later turned out to overlap with the moratorium. When the original arbitrator's mandate ended and the Bombay High Court appointed a substitute arbitrator under Section 15(2) of the Arbitration Act, the High Court also went further and declared all arbitral proceedings held during that seven-date window a "nullity" because they occurred during the moratorium, prompting this appeal.

Decision Breakdown

The Supreme Court held that under Section 15(2) of the Arbitration Act, a court's role when substituting an arbitrator is narrow. It is not an appellate power to invalidate the substituted arbitrator's prior orders, and Sections 15(3) and 15(4) make clear that earlier proceedings and orders remain valid despite a change in the tribunal's composition unless the parties agree otherwise. Relying on its own five-judge bench ruling that the Arbitration Act is a "self-contained code," the Court found the High Court had exceeded its jurisdiction under Section 15(2) by effectively setting aside Section 16 and Section 17 orders of the tribunal outside the appeal mechanism specifically provided under Section 37 of the Act. Because significant time had passed and third-party home-buyers had already acquired rights in the flats sold pursuant to the arbitral orders, the Court invoked its special power under Article 142 of the Constitution to declare those transactions lawfully valid, while otherwise allowing the substitute arbitrator to continue the proceedings. The appeal was accordingly allowed in part, setting aside only the "nullity" finding.

Lesson Learnt

A court substituting an arbitrator under Section 15(2) of the Arbitration Act cannot use that occasion to invalidate the earlier arbitral tribunal's orders: challenges to arbitral orders must go through the specific appeal routes the Act provides (such as Section 37), and courts should be cautious not to unsettle transactions that innocent third parties have already relied upon.

Company & Insolvency LawDelhi High Court

M/S Meena Steels Limited vs. Punjab National Bank

The Court held that Section 125(2)(h) applies to money received by a company for allotment of securities, not to a refund arising from a court-sanctioned reduction of share capital, so the Bank's reliance on it was misplaced. Since the earlier orders had already been passed after considering the material on record and no error apparent on the face of the record was shown, the Court found no ground for review and dismissed the Bank's petition.

Decided 8 Oct 2026Read case
Company & Insolvency LawSupreme Court of India

Greenopolis Welfare Confederation v. Rakesh Kumar Gupta

The Supreme Court held that once an insolvency petition is admitted, the proceedings become proceedings "in rem" affecting all creditors and stakeholders, not just the original applicant, so the original applicant cannot simply withdraw, but if fraud and collusion are found, the Adjudicating Authority (AA) can and should disallow that fraudulent applicant from continuing, while deciding separately whether the wider insolvency process itself should still continue to protect other genuine stakeholders like homebuyers. The Court allowed this appeal in part, set aside the NCLAT's blanket recall of the entire CIRP, and restored the insolvency proceedings to the Adjudicating Authority, directing it to now decide afresh, after hearing the resolution professional, the committee of creditors, and the homebuyers, whether the CIRP should continue in view of the confirmed fraud, and to do so expeditiously given how long the case has run.

Decided 30 Sept 2026Read case
Company & Insolvency LawSupreme Court of India

M/S ASJ Finsolutions Pvt. Ltd. v. Vikram Bajaj

The Supreme Court upheld the NCLAT's decision and dismissed the appeal. It held that the e-auction notice explicitly provided for forfeiture of the entire amount paid, including the EMD, if a successful bidder failed to pay the balance sale consideration on time, and forfeiture followed automatically once that default occurred. The Court rejected the appellant's reliance on the "Triple Test" (rigged auction, lack of genuine bidder capacity, or extraneous prevention), finding none of those circumstances applied here, and held that a mere assertion of willingness to pay does not substitute for demonstrated financial capacity. The argument that liquidation regulations cap EMD at 10% of reserve price did not help the appellant, since it had voluntarily agreed to the auction notice's forfeiture clause covering the full deposit, not just the EMD.

Decided 28 Sept 2026Read case
Company & Insolvency LawSupreme Court of India

Regional Provident Fund Commissioner-II v. Mamta Binani & Ors.

The Supreme Court agreed that the NCLAT correctly read Section 61(2) as allowing no condonation beyond 45 days, and that its own precedents (National Spot Exchange, Tata Steel) were correctly stated but factually distinguishable since those cases involved litigant fault, not tribunal system failure. Here, the delay was caused entirely by a backend/OTP failure in the NCLAT's own e-filing system, as confirmed by the NCLAT Registry's own report. Invoking the principle "actus curiae neminem gravabit" (an act of the court shall harm no one), the Court held that limitation runs against a litigant only when the court/tribunal's own systems are actually capable of receiving filings; when the tribunal's system itself fails, the litigant should not be penalised. It set aside the NCLAT's order and restored the appeal for fresh consideration, directing that the date of the first bona fide e-filing attempt be treated as the date of presentation.

Decided 10 Sept 2026Read case
Company & Insolvency LawSupreme Court of India

M/S Kerala Industrial Infrastructure Development Corporation v. Central Board of Trustees and Anr.

The Court reaffirmed settled law that Provident Fund and Gratuity dues of workmen must be paid in full by the resolution applicant, since these funds are not part of the liquidation estate and cannot be subjected to the insolvency law's "waterfall" distribution mechanism. On the question of whether "damages"/penalty under Section 14B of the EPF Act for delayed payment is automatic and mandatory, or whether the authority has discretion to reduce or waive it, the Bench found itself doubting an earlier Supreme Court decision (Horticulture Experiment Station Gonikoppal) which had held such penalty to be automatic. Rather than deciding this specific legal question itself, the Bench referred it to a larger bench for authoritative resolution, while clarifying the appellants remain free to separately seek waiver/reduction of penalty from the Central Board under the statute's second proviso to Section 14B. As practical interim relief, the Court directed the appellant companies to pay the outstanding EPF dues (with Section 7Q interest) in four quarterly instalments running from December 2026 to September 2027, failing which EPFO could proceed with recovery.

Decided 9 Sept 2026Read case
Company & Insolvency LawSupreme Court of India

The Authorised Representative for Granite Gate Properties Private Limited (Ms. Rakesh Verma) v. M/s New Okhla Industrial Development Authority

The Supreme Court held that NOIDA's lease with the original developer existed to serve a public welfare purpose, providing housing and industrial infrastructure, not pure profit-making, and that the penalty/time-extension charges were meant to deter and punish a defaulting developer, not innocent homebuyers or a new resolution applicant who had no role in the original default. Since the delay was solely the fault of the now-insolvent original developer, and the homebuyers and SRA had themselves funded and revived the stalled project, it would be unjust to pass on the developer's "past sins" as insolvency-resolution costs. The Court set aside the NCLAT's direction treating the time-extension charges as CIRP costs, and separately rejected NOIDA's own appeal for extending those penalty charges up to ten years under its newer, harsher policy. Granite Gate's appeal was allowed and NOIDA's appeal was dismissed.

Decided 3 Sept 2026Read case